FG Approves N453bn for Kano-Maradi Rail Construction, N510m for NPA Rescue Vans

The Federal Executive Council (FEC) has approved a total of N453.90 billion for the purchase of rolling stock, operational and maintenance equipment for the Kano-Maradi standard gauge rail line currently under-construction.

-Advertisement- WhatsApp Image 2025 04 26 at 10.51.58 PM

The Nigerian Ports Authority also got the approval of N510,934,600 for customised Fire Service search and rescue vans for extrication of accident victims for Rivers Ports in Port Harcourt, Lagos Port Complex, Tincan Island Port and the Marina headquarters, Lagos.

The Minister of Transportation, Mu’azu Sambo disclosed this to State House Correspondents today after the FEC meeting chaired by President Muhammadu Buhari at the Presidential Villa, Abuja.

Sambo explained that β€œThe Federal Ministry of Transportation this afternoon presented two memoranda to council on behalf of two of its agencies.

“The first agency was the Nigerian Ports Authority, which sought to provide for the award of a contract for the construction and supply of customised Fire Service search and rescue vans for extrication of accident victims for Rivers ports in Port Harcourt, Lagos Port Complex, Tincan Island Port and the Marina headquarters, all in Lagos.

ALSO READ -  Comptroller Jalo Takes Over at FOU Zone B Kaduna

β€œCouncil considered the memorandum and approved the award of the contract as recommended and reviewed by the Bureau of Public Procurement and the sum of N510,934,600 Naira inclusive of seven and a half per cent VAT and with a completion period of nine months in favour of Messrs All Works Commercial Company Limited”.

-Advertisement- ads3

He noted that the second memorandum presented by the Ministry was for the ultimate management by the Nigerian Railway Corporation (NRC).

β€œThe memorandum sought the council’s consideration and approval for the award of contract for the procurement of rolling stock, operation or maintenance equipment for the Kanio-Maradi standard gauge rail line that is currently under construction.

β€œThe contract was awarded to MSSRs Mota Engineering Nigeria Limited, who are the contractors handling this particular project in the sum of $984,722,302.5 inclusive of seven and a half per cent VAT with a completion period of four years”, he said.

Ismail Aniemu

Ismail Aniemu, Publisher of JournalNG and ghost writer, is a maritime journalist of over two decades' of practice with multidisciplinary background. He holds a masters degree in Transport Management from Ladoke Akintola University of Technology(LAUTECH) with bias for logistics. He is also an alumnus of the Times Journalism Institute where he obtained a post graduate diploma in Journalism. Email: ismail.aniemu@aol.com